Sateba UK (previously SBC Rail) won the £10 million contract to provide concrete sleepers to AMEC SPIE Rail Systems, one of the organisations involved in building the high-speed Channel Tunnel Rail Link through Kent, also known as HS1.
Project
Following the opening of the Channel Tunnel in May 1994, the Channel Tunnel Rail Link (HS1) was commissioned to reduce the journey time from London to the Channel Tunnel portal at Dollands Moor, near Folkestone.
The 109km (68 mile) high-speed line would be built in two sections. Section 1 started in October 1998 and was completed in September 2003. Section 2 started in July 2001 and the complete Channel Tunnel Rail Link was opened in November 2007.
The present journey from London St Pancras to Gard du Nord in Paris now takes an average of 2hrs 22 minutes!