Sateba UK (previously SBC Rail) were selected to provide a proven, quick fit, cost effective alternative to floating slab track on certain stretches of the Elizabeth Line, Crossrail project.
A joint venture called ATC comprising of Alstom, Transport Sud Ouest and Costain Limited won the Crossrail contract to deliver the Elizabeth Line.
Project
The Elizabeth Line runs from Reading and Heathrow in the West, to Abbey Wood and Shenfield in the East.
Up to 40 metres deep in places, the route covers 73 miles (117.5km) and includes 26 miles (42km) of tunnels.
Tunnelling began in May 2012 and the line was completed in May 2022.
Challenge
The line runs through some of the existing underground landscape and under some iconic historic buildings along its route. So the reduction of any noise and vibration was a key consideration for the design and installation, and selection of rail track products.
Floating Slab Track is traditionally used to help mitigate the vibration of trains running through populated areas, but ATC wanted something quicker and more cost effective system that would still help reduce noise and vibration.